The 70% rule formula
Take a house that will be worth $250,000 after repairs and needs $40,000 of work:
$135,000 is the most a flipper following the rule should pay. Everything above it comes out of their profit.
Where the 30% actually goes
The rule leaves 30% of ARV, $75,000 here, between the purchase-plus-repairs and the sale price. That isn't profit. Here's a typical breakdown for this flip, assuming a hard-money loan for 90% of the price plus the full rehab at 11% interest and 2 points, a six-month project, and about 7% in selling costs:
| After-repair value (sale price) | $250,000 |
| Purchase price (the 70% offer) | − $135,000 |
| Repairs | − $40,000 |
| The 30% cushion | $75,000 |
| Closing costs to buy (~2%) | − $2,700 |
| Loan points (2% of $161,500) | − $3,230 |
| Interest (11%, 6 months) | − $8,882 |
| Taxes, insurance and utilities while you hold | − $3,000 |
| Agent commissions (~5%) | − $12,500 |
| Closing costs and transfer taxes to sell (~2%) | − $5,000 |
| Profit | $39,688 |
Almost half the cushion, about $35,300, goes to costs. The flipper keeps about $39,700, roughly 16% of the sale price. That profit is also the buffer for everything that goes wrong.
What a surprise does to it
- Rehab runs 20% over ($8,000 more, borrowed on the same loan): profit drops to about $31,100.
- The project takes 10 months instead of 6: extra interest and holding costs bring profit to about $31,800.
- Both happen: profit is about $22,900, and that's before a price cut to sell.
That's why the rule exists. The 30% looks generous until you price out a real project.
When 70% is the wrong number
Cheap houses: use 60–65%
On a $100,000 ARV house with $25,000 of work, 70% gives a max offer of $45,000. Same loan terms and timeline, and the flip makes about $14,200. Holding costs and taxes don't shrink much on a cheaper house, and one surprise can wipe that out. At 60%, the offer is $35,000 and profit is about $25,100, a much safer margin for the same work.
Expensive houses: 75% can work
On a $500,000 ARV house with $60,000 of work, 75% gives a max offer of $315,000. Costs come to about $70,000 and profit is about $54,900, only 11% of the sale price but plenty of dollars to absorb a surprise. This is why flippers at higher price points often pay more than 70%.
Other reasons to adjust
- Go lower for heavy rehabs (structural, full systems), long permit timelines, slow markets, or expensive financing.
- Go higher for light cosmetic work, very fast markets, or cash purchases with no loan costs.
- Check your actual numbers. If you know your real costs, skip the rule and calculate profit directly, like the breakdown above.
For wholesalers: your buyer's 70% is your ceiling
If you're wholesaling, the 70% number is your cash buyer's max price, not yours. Subtract your assignment fee to get your max offer. On the $250,000 house, a $10,000 fee means contracting at $125,000 or less. The wholesale MAO guide covers this in detail.
Common 70% rule mistakes
- Treating 30% as profit. Close to half of it goes to costs, as the breakdown shows.
- Inflating the ARV. The rule is only as good as your comps. Use recent sales of renovated, similar houses close by, not the Zestimate.
- Underestimating repairs. Round up. Overruns are more common than underruns.
- Using 70% on every price point. Adjust for cheap and expensive houses as shown above.
- Ignoring time. At today's interest rates, every extra month costs real money.
To check a deal at 65%, 70% and 75%, use the free 70% rule calculator. And if the house might work better as a rental, see how to analyze a Zillow listing in 5 minutes.